Construction Updates, Nov 2019.

Construction in full-swing

OC has been received part for 22 storeys, and a number of customers have taken possession of their homes and moved in. With approvals in place, construction of upper floors is also progressing as planned.

Monte Carlo:

Detailed updates:

RCC work completed up to 33rd Floor
Internal RCC completed up to 30th storey
Ground floor entrance lobby and lift lobby 100% completed
Swimming pool & club area work completed
Ground Floor Driveway area completed
External painting up to 29th floor – 80% completed
Plumbing Work till 29th floors– 100% completed
Waterproofing completed up to 22nd floor

Monte Carlo:

Detailed updates:

RCC work completed up to 33rd Floor
Internal RCC completed up to 30th storey
Ground floor entrance lobby and lift lobby 100% completed
Swimming pool & club area work completed
Ground Floor Driveway area completed
External painting up to 29th floor – 80% completed
Plumbing Work till 29th floors– 100% completed
Waterproofing completed up to 22nd floor